Question: Question 1 8 ( 1 point ) During the project execution phase, what is the primary purpose of monitoring and controlling project risks?To assign blame

Question 18(1 point)During the project execution phase, what is the primary purpose of monitoring and controlling project risks?To assign blame for risk occurrenceTo create additional risksTo identify and respond to new risks and assess the effectiveness of risk responsesTo update the project schedule