Question: Question 1 8 5 pts What is the cost performance index for a project that has a TBC = $ 5 0 , 0 0

Question 18
5 pts
What is the cost performance index for a project that has a TBC =$50,000,aCEV=$25,000, a CAC=$20,000, and CBC=$22,000.q,
CPI =0.8
CPI =0.91
CPI =1.1
CPI =1.25