Question: Question 1 9 ( 1 2 . 5 points ) Calculations for this question should be uploaded. Please make sure that the file is legible.

Question 19(12.5 points)
Calculations for this question should be uploaded. Please make sure that the file is legible.
A wastewater treatment plant is designed to remove 1,500kg of BOD per day and nitrify 200kg of Ammonia with no denitrification
i)Calculate the Volume required when the BOD loading rate is 1.2kgm3? day.
ii) If the MLSS concentration is 3000mgI what is the F to M ratio? is this sufficient for nitrification to take place.
iii)if the waste activated sludge concentration is 2.5 times higher than the MLSS what volume of sludge must be wasted to maintain an SRT of 15 days.
iv)If the BOD to biomass ratio in the sludge is 1.42. What volume of air is required to supply enough oxygen for both the BOD and the ammonia oxidation?
v) If the system was converted to a Membrane Bioreactor and the MLSS increased to 11,500mgI how much additional BOD could be treated per day?
Question 1 9 ( 1 2 . 5 points ) Calculations for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!