Question: Question 1 9 ( 6 points ) Saved Refer to the information in Q 1 8 . The project manager would like to reduce the

Question 19(6 points)
Saved
Refer to the information in Q18.
The project manager would like to reduce the project duration, which has been determined in Q18, to 10 weeks. What's the optimal sequence of activities to be crashed such that the project can be done in 10 weeks?
B-G-G-G-C-D
B-C-D-G-G-G
G-G-G-B-D
G-G-G-F-C