Question: Question 1 : A contractor has performed extra work on a project but the owner refuses to pay for the work, arguing that payment for
Question :
A contractor has performed extra work on a project but the owner refuses to pay for the work, arguing that payment for the extra work is already covered under existing bid items. Which of the following legal doctrines can the contractor assert in court to seek payment for the extra work? Mark all that apply.
Promissory Estopple
Contract Implied in Fact
Unjust Enrichment
Cardinal Change
Quantum Meruit
Detrimental Reliance
Question :
Tradespecific words or terms in a contract are interpreted according to theirBlank meanings Choose all that apply.
customary
dictionary
reasonable
usage