Question: QUESTION 1 - > A linkage relationship where the completion of the successor activity depends on the completion of the predecessor activity is called a

QUESTION 1 - > A linkage relationship where the completion of the successor activity depends on the completion of the predecessor activity is called a ________ .

a.

start-to finish dependency

b.

finish-to-start dependency

c.

finish-to-finish dependency

d.

start-to-start dependency

QUESTION -> 2

  1. To crash a project, which of the following principles apply? 1) Focus on the critical path(s) when trying to shorten the duration of a project, 2) Select the least expensive way to do it 3) Crash non-critical activities

    a.

    All three are correct

    b.

    only 1 and 3 are correct

    c.

    only 1 and 2 are correct

    d.

    only 1 is correct

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!