Question: QUESTION 1 - > A linkage relationship where the completion of the successor activity depends on the completion of the predecessor activity is called a
QUESTION 1 - > A linkage relationship where the completion of the successor activity depends on the completion of the predecessor activity is called a ________ .
| a. | start-to finish dependency | |
| b. | finish-to-start dependency | |
| c. | finish-to-finish dependency | |
| d. | start-to-start dependency |
QUESTION -> 2
-
To crash a project, which of the following principles apply? 1) Focus on the critical path(s) when trying to shorten the duration of a project, 2) Select the least expensive way to do it 3) Crash non-critical activities
a. All three are correct
b. only 1 and 3 are correct
c. only 1 and 2 are correct
d. only 1 is correct