Question: Question 1 A project has 7 9 activities but only 9 activities are discussed here. Activity K , duration = 3 9 days, I P

Question 1
A project has 79 activities but only 9 activities are discussed here.
Activity K, duration =39 days, IP= not given
Activity Q, duration =27 days, IP= not given
Activity D, duration =16 days, IP= not given
Activity L, duration =36 days, IP=K
Activity P, duration =55 days, IP=K,Q,D
Activity A, duration =33 days, IP=D
Activity M, duration =28 days, IP=L,P
Activity N, duration =11 days, IP=L,P
Activity R, duration =16 days, IP=P,A
If LF of M=225,LF of N=220, and LF of R=214, find LS(D)