Question: Question 1 A task has a normal duration of 10 days and a crash duration of 8 days. Its normal cost is $40 and its

Question 1 A task has a normal duration of 10 days and a crash duration of 8 days. Its normal cost is $40 and its crash cost is $120. What is the crash cost per day

Question 2 :

  1. An activity has an early start (ES) of day 3, a late start (LS) of day 13, and early finish (EF) of day 9, and late finish (LF) of day 19. The activity:

Question 3 :

  1. A Schedule Performance Index (SPI) of 0.75 means:

Question 4 :

  1. Earned Value (EV) for a new optic radar design project is calculated at $100,000 and the Actual Cost (AC) is $80,000. The Budget at Completion (BAC) is estimated at $200,000. What is the current CPI on this project?

Question 5:

  1. Given that, a project with Earned Value (EV) = 1000, Actual Cost (AC) = 700, and Planned Value (PV) = 800, which of the following is correct calculation of the schedule variance (SV).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!