Question: Question 1 ABC Company has a plant for meat processing. The factory can produce 4,700 packs per day. The effective capacity is 4,300. The actual
Question 1 ABC Company has a plant for meat processing. The factory can produce 4,700 packs per day. The effective capacity is 4,300. The actual output is 4,076 packs. The factory has 5 production lines which operate 6 days per week (6th day is half-day), with one 8-hour shift per day. Compute for the following: -Design capacity in a month -Efficiency per day -Utilization per week and month -Evaluate and explain the results of the Utilization per month Question 2. Job Job time Due date A 13 45 B 10 16 C 7 22 D 5 17 E 14 39 F 17 27 G 11 19 The table contains information concerning the 7 jobs that are arrived and awaiting processing at a work center. Determine the sequence using LPT, EDD & CR. Then compute the Avg. job in the systems and lateness, and utilization. What is your conclusion?