Question: Question 1 B Harley - Davidson has its engine assembly plant in Milwaukee and its motorcycle assembly plant in Pennsylvania. Engines are transported between the

Question 1B
Harley-Davidson has its engine assembly plant in Milwaukee and its motorcycle assembly plant in Pennsylvania. Engines
are transported between the two plants using trucks, with each trip costing $1,500. The motorcycle plant assembles
and sells 250 motorcycles each day. Each engine costs $600, and Harley incurs a holding cost of 25 percent per year.
What is the Optimal Lot Size (Economic Order Quantity (EOQ)=Q**?
What is the Optimal Number of Orders per year?
What is the Total Annual Ordering and Holding Cost?
What is the Average Flow Time?
Question 2
Using EOQ, Ducati motorbikes is building a plant in the US and will import the engines from Italy. Engines are
transported between the two locations using planes and trains, with each trip costing $2,500. The motorcycle plant
assembles and sells 150 motorcycles each day. Each engine costs $750, and Harley incurs a holding cost of 15 percent
per year.
What is the Annual Demand (D)?
What is the Cost per Unit (C)?
What is the Fixed Cost Incurred per Order (S)
What is the Ordering Cost?
What is the Annual Holding Cost (hC)?
What is the Total Inventory Cost?
What is the Cycle Inventory of engines at Ducati?
What is the Average Flow Time resulting from the Cycle Inventory?
 Question 1B Harley-Davidson has its engine assembly plant in Milwaukee and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!