Question: question # 1 C. 3.C (* = easy; ** = moderate; ; *** advanced) Problems for Section 13.4: Kanban Systems 1. (*) Suppose you have

question # 1
question # 1 C. 3.C (* = easy; ** = moderate; ;
C. 3.C (* = easy; ** = moderate; ; *** advanced) Problems for Section 13.4: Kanban Systems 1. (*) Suppose you have the following information: Demand rate (D) = 750 units per hour Lead time (T) = 40 hours Container capacity (0) = 1,000 units Safety factor (x) = 10% How many kanban production cards are required? b. 28 a. 59 c. 30 d. 33