Question: Question 1 : ChoiceBetweenAlternativesPro _ Spring 2 5 _ WS 6 _ Q 1 Your city is planning a stormwater drainage improvement project to mitigate

Question 1: ChoiceBetweenAlternativesPro_Spring25_WS6_Q1
Your city is planning a stormwater drainage improvement project to mitigate flooding in residential and commercial areas, which has a construction cost due at the end of the first year of \(\$ 8\) million, second year of \(\$ 5\) million, and third year of \(\$ 3\) million. It is completed at the end of the third year and thereafter incurs an annual operating cost of \(\$ 386000\) per year (due at the end of each year). Benefits from the project, such as traffic delay reduction and safety improvements, also begin during the fourth year and are valued at \(\$ 2.3\) million available at the end of that year, growing at a \(2.7\%\) compound rate of increase out to the service life (analysis period) of 22 years. The compounded annually interest rate is \(5\%\). Compute the following: present worth cost, present worth benefit, and present worth net benefit of the project.
Question 1
Calculate the present worth of the cost (in million \$)
(Round your answer to six decimal places.)
Question 2
Calculate the present worth of the benefit (in million \$)
(Round your answer to six decimal places.)
402945.255874
Question 3
Calculate the present worth of the net benefit (in million \$)
(Round your answer to six decimal places.)
Question 4
How much will the increase in the net benefit (in percentage) be if the service life of the project is extended to 43 years?
(Report your answer in decimal, e.g.0.05 for \(5\%\). Round your answer to 6 decimal places)
Question 1 : ChoiceBetweenAlternativesPro _

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!