Question: Question 1: Consider a project for which you are the PM. You have to oversee the desgin and installation of a grid-tied solar power system
Question 1:
Consider a project for which you are the PM. You have to oversee the desgin and installation of a grid-tied solar power system for a plant. Create a report (1,500-2,000 words) for the above based on the points below:
i. Define the objectives and scope of work of the project (work included/excluded and the context of work)
ii. Define the specifications of the equipment and list the safety and regulatory requirements
iii. Create a list of activities and phases for the project (provide a WBS)
iv. Create a time management schedule for the activities (provide a Gantt chart)
v. Discuss how you might use PERT to take into account uncertainties in the duration and cost of the tasks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
