Question: Question 1: Consider the following Gantt Chart. Answer the below questions. 1-What are the various tasks? 2-When does each taskbegin and end? 3-How long is
Question 1: Consider the following Gantt Chart. Answer the below questions.
1-What are the various tasks?
2-When does each taskbegin and end?
3-How long is each taskscheduled to last?
4-Where do tasksoverlap with other tasks, and by how much?
5-What is the duration of the whole project?
6-What are the tasks dependencies?
7-Assume that a serious and unanticipated problem occurs during the project development, and task D takes 6 weeks instead of taking 2 weeks.
8-Will task E be affected and delayed? Justify your answer.
9-Will the whole project be delayed? If yes, what is the new end date of the project? Justify your answer.
Task in terms of weeks