Question: Question 1 : Consider the following project: table [ [ , , Duration ( days ) , Total cost ( $ ) ] ,

Question 1:
Consider the following project:
\table[[,,Duration (days),Total cost ($)],[Activity,IPA,Normal,Crash,Normal,Crash],[A,---,10,8,100,120],[B,--,6,4,80,90],[C,--,3,1,95,125],[D,A,12,9,140,200],[E,B,6,3,65,115],[F,B,C,8,8,75,75],[G,E,F,18,13,228,318]]
a. Based on the normal time, draw the activity on an arrow network for this network.
b. Identify the critical path and the expected completion time.
c. Based on the normal time, draw the Gantt chart and show the critical path on the chart.
d. Determine the crashed duration for this project and the cost associated with it.
e. Based on the crashed time, draw the activity on an arrow network for this project.
f. Using MS project, perform part c
 Question 1: Consider the following project: \table[[,,Duration (days),Total cost ($)],[Activity,IPA,Normal,Crash,Normal,Crash],[A,---,10,8,100,120],[B,--,6,4,80,90],[C,--,3,1,95,125],[D,A,12,9,140,200],[E,B,6,3,65,115],[F,B,C,8,8,75,75],[G,E,F,18,13,228,318]] a.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!