Question: Question 1: Critical Path Method. Provide manual answer. Do not use Excel or MS Project. Submit pdf file. Below is information about a project to
Question 1:Critical Path Method. Provide manual answer. Do not use Excel or MS Project.
Submit pdf file.
Below is information about a project to implement a new manufacturing cell to assemble personal digital assistant devices.
ACTIVITY | DURATION | PREDECESSORS | ES | EF | LS | LF | TOTAL SLACK |
A. Design Process Requirements | 2 | --- | |||||
B. Benchmark Competitors Processes | 4 | A | |||||
C. Prepare Benchmark Report | 1 | B | |||||
D. Design Process and Layout | 2 | A | |||||
E. Finalize design and setup manf. Cell | 2 | C, D | |||||
F. Select and train operators | 1 | D | |||||
G. Pilot test new process | 2 | E, F | |||||
H. Finalize process design | 1 | G |
1.Draw a network diagram.
2.Identify the ES, EF, LS, LF and slack times in the table using the critical path method.
3.During the initial stages of the project, a new set of requirements were discovered that would extend the process and layout design activity from 2 to 6 months. The operations group which initiated these requirement changes argues that they would not impact the project duration. Is this true? Justify your answer.