Question: Question 1: Critical Path Method. Provide manual answer. Do not use Excel or MS Project. Submit pdf file. Below is information about a project to

Question 1:Critical Path Method. Provide manual answer. Do not use Excel or MS Project.

Submit pdf file.

Below is information about a project to implement a new manufacturing cell to assemble personal digital assistant devices.

ACTIVITY

DURATION

PREDECESSORS

ES

EF

LS

LF

TOTAL SLACK

A. Design Process Requirements

2

---

B. Benchmark Competitors Processes

4

A

C. Prepare Benchmark Report

1

B

D. Design Process and Layout

2

A

E. Finalize design and setup manf. Cell

2

C, D

F. Select and train operators

1

D

G. Pilot test new process

2

E, F

H. Finalize process design

1

G

1.Draw a network diagram.

2.Identify the ES, EF, LS, LF and slack times in the table using the critical path method.

3.During the initial stages of the project, a new set of requirements were discovered that would extend the process and layout design activity from 2 to 6 months. The operations group which initiated these requirement changes argues that they would not impact the project duration. Is this true? Justify your answer.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!