Question: Question 1 : Data for precedence network are given below along with the activity resource rates. Level the resources. Check your levelling using minimum moment.

Question 1:
Data for precedence network are given below along with the activity resource rates. Level the resources. Check your levelling using minimum moment.
\table[[Activity,Duration,Resource,\table[[Depends],[on]]],[A,7,12,-],[B,5,8,-],[C,4,7,-],[D,8,15,A],[E,7,6,B],[F,6,5,C],[G,13,4,C],[H,8,9,D]]
Question 2:
If the maximum recourses are 21, use Wiest method to reschedule the project accordingly.
Question 1 : Data for precedence network are