Question: Question 1: Epic Scenery Studios has learned that its project is needed in 7 days, and so plans must be drawn up to meet this
Question 1:
Epic Scenery Studios has learned that its project is needed in 7 days, and so plans must be drawn up to meet this new deadline. Of the nine original tasks, four of them could be crashed, but at differing levels of expense.
| Task | Description | Normal Duration (Days) | Crash Time (Days) | Crash Cost ($) |
| B | Purchase & dye fabric | 3 | 2 | $1000 |
| C | Build stage | 4 | 1 | $2000 |
| D | Sew fabric & frame backdrop | 2 | 1 | $500 |
| F | Paint stage | 2 | 1 | $800 |
Calculate the length of each path through Epic's project, provided that each task is completed in a normal amount of time. Based on your calculations, which of the following statements is correct?
Question 1 options:
|
|
Project completion time is 10 days
|
|
|
Time length for Path A-E-I is 5 days
|
|
|
Time length for Path A-E-I is 8 days
|
|
|
Time length for Path A-E-I is 3 days
|
|
|
Time length for Path A-C-F-G-H-I is 8 days
|
|
|
Time length for Path A-C-F-G-H-I is 9 days
|
|
|
only a, d, f are correct
|
|
|
Only a is correct
|
|
|
a, b, and e are correct
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
