Question: Question 1: Epic Scenery Studios has learned that its project is needed in 7 days, and so plans must be drawn up to meet this

Question 1:

Epic Scenery Studios has learned that its project is needed in 7 days, and so plans must be drawn up to meet this new deadline. Of the nine original tasks, four of them could be crashed, but at differing levels of expense.

Task Description Normal Duration (Days) Crash Time (Days) Crash Cost ($)
B Purchase & dye fabric 3 2 $1000
C Build stage 4 1 $2000
D Sew fabric & frame backdrop 2 1 $500
F Paint stage 2 1 $800

Calculate the length of each path through Epic's project, provided that each task is completed in a normal amount of time. Based on your calculations, which of the following statements is correct?

Question 1 options:

Project completion time is 10 days

Time length for Path A-E-I is 5 days

Time length for Path A-E-I is 8 days

Time length for Path A-E-I is 3 days

Time length for Path A-C-F-G-H-I is 8 days

Time length for Path A-C-F-G-H-I is 9 days

only a, d, f are correct

Only a is correct

a, b, and e are correct

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!