Question: QUESTION 1 Figure to accompanv Table 7 . 1 Table 7 . 1 For the followng 5 questions use the above tables: Calculate the slack

QUESTION 1
Figure to accompanv Table 7.1
Table 7.1
For the followng 5 questions use the above tables:
Calculate the slack time for activity D.
Provide the earliest finish time for activity A.
State the latest start time for activity E.
Calculate the activity time for activity F.
Based on the above information, select the one which is the critical path.
A) ABDG
B) ABEG
C) ACEG
D) ACFG