Question: Question 1: From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path.
Question 1: From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
| ID | DESCRIPTION | PREDECESSOR | TIME |
| A | Survey site | None | 2 |
| B | Install drainage | A | 5 |
| C | Install power lines | A | 3 |
| D | Excavate site | B, C | 4 |
| E | Pour foundation | D | 3 |