Question: QUESTION 1 Given the following network diagram, which activity, or activities, would you crash so that the original project time will be reduced by 1
QUESTION
Given the following network diagram, which activity, or activities, would you crash so that the original project
time will be reduced by day in the most economic ie cheapest way possible?