Question: Question 1: Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time, overtime, subcontract and backorders. Regular

Question 1:

Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time, overtime, subcontract and backorders. Regular time is limited to 150 units per month (Cost per Unit = $30 ). Overtime is limited to a maximum of 60 units per month (Cost per Unit =$45). Units purchased from the subcontractor (Cost per Unit = $38 ) cannot exceed 70 per month and the total purchases from the subcontractor over the 6 month period cannot be over 220 units. Backorders cannot exceed 70 units in any given month (Cost per Unit = $5 ) and must be no more than 40 in Period 6. Average Inventory Holding cost per Unit = $10. Forecasted Demand as well as Beginning and desired Ending Inventory are listed in the table below.

Month

1

2

3

4

5

6

Total

Regular Output

Overtime Output

Subcontract

Beginning Inventory

30

Total Available for Sale

Less Forecast

180

210

310

170

150

160

Plus Backlog-Current Period

Less Backlog-Previous Period

Ending Inventory

10

Average Inventory

Question 1 options:

Aggregate Planning Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time, overtime, subcontract and backorders. Regular time is limited to 150 units per month (Cost per Unit = $30 ). Overtime is limited to a maximum of 60 units per month (Cost per Unit =$45). Units purchased from the subcontractor (Cost per Unit = $38 ) cannot exceed 70 per month and the total purchases from the subcontractor over the 6 month period cannot be over 220 units. Backorders cannot exceed 70 units in any given month (Cost per Unit = $5 ) and must be no more than 40 in Period 6. Average Inventory Holding cost per Unit = $10. Forecasted Demand as well as Beginning and desired Ending Inventory are listed in the table below.

Month

1

2

3

4

5

6

Total

Regular Output

Overtime Output

Subcontract

Beginning Inventory

30

Total Available for Sale

Less Forecast

180

210

310

170

150

160

Plus Backlog-Current Period

Less Backlog-Previous Period

Ending Inventory

10

Average Inventory

Required: Find the Minimum Cost Production Plan by Creating a Spreadsheet in Excel. Use Solver to find the Minimum Cost Solution. Leave a copy of your Spreadsheet in the DropBox. Total Cost Month 1 = Total Cost Month 2 = Total Cost Month 3 = Total Cost Month 4 = Total Cost Month 5 = Total Cost Month 6 = Total Cost All Periods =

Question 2:

Below is a table of times for Taxis (A to H) to reach Customers (1 to 8) who need a ride home after a night on the town. The goal is to Minimize the time it takes for all of the Taxis to reach their Customers. Only one Taxi will be sent to each Customer and each Customer needs only one Taxi.

Taxi / Cust

1

2

3

4

5

6

7

8

A

19

16

3

10

19

12

16

8

B

14

4

4

7

18

8

7

4

C

13

3

15

12

14

19

14

5

D

14

14

13

4

9

17

9

11

E

5

16

16

14

17

19

4

6

F

19

12

6

13

7

18

16

7

G

12

12

9

15

18

8

13

15

H

7

12

18

14

2

4

5

18

The optimal solution to this problem requires the following:

Taxi A picks up Customer = Taxi B picks up Customer = Taxi C picks up Customer = Taxi D picks up Customer = Taxi E picks up Customer = Taxi F picks up Customer = Taxi G picks up Customer = Taxi H picks up Customer = Minimum Cost =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!