Question: Question 1 : ISE 3 6 1 SPRING 2 0 2 3 ASSIGNMENT DUE DATE: 1 3 / 0 6 / 2 0 2 3

Question 1: ISE 361 SPRING 2023 ASSIGNMENT DUE DATE: 13/06/202323:596 jobs must be processed through the same machine center and they are labeled as A, B, C, D, E and F according to the order they entered the system. Assume the current time is 1:00 P.M. The following table shows the processing times and due dates for each job. JOB A B C D E F PROCESSING TIME (in minutes)253015503545(i) FCFS (ii) SPT (iii) EDD (iv) CR (v) Moore's Algorithm DUE DATE 2:05 P.M.1:50 P.M.1:30 P.M.4:00 P.M.3:05 P.M.2:45 P.M. a) Determine the sequences and compute mean flow time, average tardiness, maximum lateness, and the number of tardy jobs for b) Which sequence you found in (a) would you use to satisfy the following objectives? (i) Minimize mean flow time (ii) Minimize average tardiness (iii) Minimize max lateness (iv) Minimize the number of tardy jobs 6 jobs must be processed through the same machine center and they are labeled as A, B, C, D, E and F according to the order they entered the system. Assume the current time is 1:00 P.M. The following table shows the processing times and due dates for each job. a) Determine the sequences and compute mean flow time, average tardiness, maximum lateness, and the number of tardy jobs for (i) FCFS (ii) SPT (iii) EDD (iv) CR (v) Moore's Algorithm b) Which sequence you found in (a) would you use to satisfy the following objectives? (i) Minimize mean flow time (ii) Minimize average tardiness (iii) Minimize max lateness (iv) Minimize the number of tardy jobsQuestion 2:
6 jobs must be processed through the same machine center and they are labeled as A, B, C, D, E, and F according
to the order they entered the system. Assume the current time is 8:00 A.M. The following table shows the
processing times and due dates for each job.
a) Determine the sequences and compute mean flow time, average tardiness, maximum lateness, and the
number of tardy jobs for
(i) FCFS
(ii) SPT
(iii) EDD
(iv)CR
(v) Moore's Algorithm
b) Which sequence you found in (a) would you use to satisfy the following objectives?
(i) Minimize mean flow time
(ii) Minimize average tardiness
(iii) Minimize max lateness
(iv) Minimize the number of tardy jobs
Please use 2-digits after decimal point in vour calculations.
 Question 1: ISE 361 SPRING 2023 ASSIGNMENT DUE DATE: 13/06/202323:596 jobs

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!