Question: Question 1 Item# What is needed# Quantity needed Item# On hand (beginning) inventory# Lot sizing# Lead time A C 1 A Week 357 A
Question 1 Item# What is needed# Quantity needed Item# On hand (beginning) inventory# Lot sizing# Lead time A C 1 A Week 357 A B 1 B Gross req. 40 20 150 C B 2 C 65 100 140 L4L 1 L4L 1 25 2 5 pts The three tables shows the master production schedule and the bill of materials of part A, and the inventory records of all the parts. There are no scheduled receipts. Given this information, what is the planned order receipt of part B in Week 6?(Only enter a number. Do not enter any units. (c)orsdemir. Copyrighted content. Cannot be posted.)
Step by Step Solution
There are 3 Steps involved in it