Question: Question 1: Mark Joshua & Sons uses an estimated overhead rate for allocating production overhead to job orders. The rate is on a machine hour
Question 1: Mark Joshua & Sons uses an estimated overhead rate for allocating production overhead to job orders. The rate is on a machine hour basis for the machining department and on a direct labour cost basis for the finishing department. The entity estimated the following for the current year:
| Machining | Finishing | |
| Production overhead cost | $10 000 000 | $8 000 000 |
| Machine hours | 200 000 | 33 000 |
| Direct labour hours | 30 000 | 160 000 |
| Direct labour cost | $900 000 | $4 000 000 |
During January, the cost record for job order no. 806 shows the following:
| Machining | Finishing | |
| Direct materials requisitioned | $14 000 | $3 000 |
| Direct labour cost | $600 | $1 250 |
| Direct labour hours | 30 | 50 |
| Machine hours | 130 | 10 |
Total costs and machine hours were as follows for the current year:
| Machining | Finishing | |
| Production overhead incurred | $10 200 000 | $7 900 000 |
| Direct labour cost | $950 000 | $3 900 000 |
| Machine hours | 220 000 | 32 000 |
Required
(a) What is the estimated overhead rate that should be used in the: (1+1)
(i) machining department?
(ii) finishing department?
(b) What is the total overhead allocated to job 806? (2)
(c) Assuming that job 806 manufactured 200 units of product, what is the unit cost of job 806? (1)
(d) What is the total amount of overapplied or underapplied overhead in each department at the end of the year? (2)
(e) Provide reasons why Mark Joshua & Sons uses two different overhead application bases. Also discuss why they might use machine hours and labour costs to allocate overhead costs. (2)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
