Question: Question 1: Part A - 8 marks, Part B - 4 marks, Part C - 3 marks) (15 Marks) A four (4) months project has
Question 1: Part A - 8 marks, Part B - 4 marks, Part C - 3 marks)
(15 Marks)
A four (4) months project has the following budget management figures:
A. Complete the table below by calculating the values for CV, CPI, SV, and SPI
Tasks
EV
PV
AC
CV
CPI
SV
SPI
month 1
$3,000
$3,500
$3,500
month 2
$9,000
$8,500
$8,000
month 3
$13,000
$12,000
$11,000
month 4
$2,500
$4,000
$3,500
month 5
$2,000
$2,000
$3,500
Earned Value Management formulas
SV= EV-PV
CV=EV-AC
SPI=EV/PV
CPI=EV/AC
B. Determine the project status by evaluating CV, CPI, SV, and SPI for each month (eg. Over budget, on budget, Under budget etc)
Tasks
Cost
Schedule
month 1
month 2
month 3
month 4
month 5
C. Is the project successful? Why or why not?