Question: Question 1 : Part a ) Create an Activity - on - Arrow ( AOA ) diagram based on the following information: Task A ,

Question 1:
Part a) Create an Activity-on-Arrow (AOA) diagram based on the following information:
Task A, duration 2, no dependency
Task B, duration 4, no dependency
Task C, duration 7, no dependency
Task D, duration 5, depends on Task A
Task E, duration 3, depends on Task B and Task C
Task F, duration 8, depends on Task C
Task G, duration 10, depends on Task D and Task E
Task H, duration 4, depends on Task E
Task I, duration 7, depends on Task F
Task J, duration 12, depends on Task H and Task I
Part b) Using the diagram you created in Part a, calculate ES, EF, LS, LF for each task.
Part c) What does 'slack' mean? Also, please calculate the amount of slack for each task.
Part d) List the tasks that appear on the critical path.
Part e) When is the project expected to be completed (project duration)?
Part f) What happens to the critical path from the network schedule created in part a if the duration of Task E
changes to 11 days?
Part g) Can a project have multiple critical paths?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!