Question: Question 1 : Part a ) Create an Activity - on - Arrow ( AOA ) diagram based on the following information: Task A ,
Question :
Part a Create an ActivityonArrow AOA diagram based on the following information:
Task A duration no dependency
Task B duration no dependency
Task C duration no dependency
Task D duration depends on Task A
Task E duration depends on Task B and Task C
Task F duration depends on Task C
Task G duration depends on Task D and Task E
Task H duration depends on Task E
Task I, duration depends on Task F
Task J duration depends on Task H and Task I
Part b Using the diagram you created in Part a calculate ES EF LS LF for each task.
Part c What does 'slack' mean? Also, please calculate the amount of slack for each task.
Part d List the tasks that appear on the critical path.
Part e When is the project expected to be completed project duration
Part f What happens to the critical path from the network schedule created in part a if the duration of Task E
changes to days?
Part g Can a project have multiple critical paths?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock