Question: Question 1: Please answer the following questions by using the information given in the table. Years 0 1 2 3 4 5 Cash Flows C
Question 1: Please answer the following questions by using the information given in the table.
| Years | 0 | 1 | 2 | 3 | 4 | 5 |
| Cash Flows | C0 | C1 | C2 | C3 | C4 | C5 |
| Project X | -9000 | 6000 | 4000 | 4000 | 0 | 0 |
| Project Y | -9000 | 2000 | 2000 | 2000 | 6000 | 6000 |
a) Calculate the payback period for each project. Which one would you choose, why?
b) Calculate the NPV of the projects at a discount rate of 5%. Which one would you choose, why?
c) Show how you would calculate the IRR for the project (It is equal to 28% for project X and 22% for project Y). Which project would you choose according to IRR method?
d) Could you please explain why IRR model makes you choose a different project than NPV method? What is your final decision?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
