In May, the city council of Oshawa, Ontario, awarded a $7.6 million contract to Build-It Corp. (BIC) to construct a new community centre in the city. The contract included a clause that provided for an early-completion bonus if BIC finished the project at least one month before the scheduled completion date of October 31.
The bonus completion schedule, together with BICs senior managements estimates as to the probability of finishing by the specified dates, follows:
Project completion dateBonus paymentEstimated probabilityPrior to July 31$400,00010%Between August 1 and 31$300,00020%Between September 1 and 30$200,00040%October 1, or later$030%
BICs year end is December 31. It reports its financial results in accordance with IFRS and uses the most likely amount to estimate variable consideration.
What transaction price should be used to recognize revenue for this contract?
A $7,800,000B $7,600,000C $7,680,000D $7,780,000
0
Feedback
Back
Next

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!