Question: Question (1) Quantitative Analysis, answer the following discussion question: (10 marks) Suggest 2 potential actions that a quantitative analyst could undertake to ensure that the
Question (1) Quantitative Analysis, answer the following discussion question: (10 marks)
- Suggest 2 potential actions that a quantitative analyst could undertake to ensure that the implementation stage of a project is successful. ( detailed explanation is required)
Question (2) : Referred to your understanding of the special cases in LP, answer the following question: ( 10 marks)
- Develop your own set of constraint equations and inequalities and use them to illustrate graphically each of the following conditions:
- No feasible solution problem (5 marks)
- An Unbounded problem (5 marks)
Question (3): Referred to the below table, solve the following questions: (10 marks)
|
| X1 | X2 | Availability per month |
| Constraint 1 | 1 | 2 | 45 |
| Constraint 2 | 3 | 3 | 87 |
| Constraint 3 | 2 | 1 | 50 |
| Maximize profit | 50 | 20 |
|
Required:
- Formulate the problem as linear program. (Objective function- your own decision variables- Constraints).(4 marks)
- Draw the problem graphically and assign the feasible region and the optimal point on the graph. (3 marks)
- Determine the optimal value of Z. (1 mark)
- What are the binding and nonbinding constraints? (1 mark)
- What is the slack for constraint (1)? (1 mark)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
