Question: Question 1 : Scheduling. ( 3 0 marks ) Use Table 4 to answer the question. A project has been defined to contain the following
Question : Scheduling. marks
Use Table to answer the question. A project has been defined to contain the following list of activities
along with their required times of completion in days.
Table
A Prepare an AOA Chart for the above Project considering FS relationship only. Remember to include appropriate dummy arrows if any. marks
BDraw a Gantt chart for the above project based on all the relationships given. marks
CProvide the critical path and state the project length. marks
DList all the distinct paths in the network? marks
Note: Can you please draw diagrams for better understanding. Thanks....