Question The Engineering School is creating a new student computer lab. The table below shows the activities required to construct a new computer lab, along with their estimated durations in weeks and predecessor activities.
tableActivityTime weeksPredecessorsOrder Furniture OFOrder Computers OCOrder Software OSOCFurniture Delivery FDOFComputer Delivery CDOCSoftware Delivery SDOSAssemble Furniture AFPR FDInstall Computers ICAF CDInstall Software ISIC SDInstall Electrical Wiring IEWPaint Room PRIEW
a Draw the project network.
b Determine the critical path using Critical Path Method.