Question: Question 1 The following table provides data for a project. Use the data to answer the following questions Activity Immediate Predecessor Time Estimates (weeks) Optimistic

Question 1

The following table provides data for a project. Use the data to answer the following questions

Activity

Immediate

Predecessor

Time Estimates (weeks)

Optimistic

Most Likely

Pessimistic

Expected

Variance

A

-

2

5

14

B

-

8

11

14

C

A

5

7

9

D

A

6

9

12

E

D, B

1

3

5

(a) Draw a network to represent the above project. (Make sure you indicate activities and their durations and don't forget the ARROWS!)

(b) What is the critical path? What is the expected completion time? What is the variance of the project completion time? (Complete the expected task time and variance of time calculations.)

(c) Which activities currently can be delayed without delaying the entire project and what are their corresponding slack times?

(d) The customer wants the project to be completed in 15 weeks. What is the probability that the project will be completed in 15 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!