Question: Question 1 The project was over, so each worker went back to her usual assignment, taking with them the notebook they were issued when the

Question 1

The project was over, so each worker went back to her usual assignment, taking with them the notebook they were issued when the project began. They never were sure whether the project had been successful or unsuccessful, but they could be positive that the project was terminated by:

Group of answer choices

Extinction.

Addition.

Integration.

Starvation.

Question 2

Which two types of project termination are reserved for successful projects?

Group of answer choices

Addition and integration

Integration and starvation

Starvation and extinction

Extinction and addition

Question 3

Of the project closeout management steps listed, the first is to:

Group of answer choices

Finish the work.

Hand over the project.

Gain acceptance for the product.

Review how it all went.

Question 4

A lessons-learned analysis is BEST described as:

Group of answer choices

An organizational learning process.

A bookkeeping process.

A personnel reassignment process.

A pressure relief process.

Question 5

In non-binding arbitration:

Group of answer choices

The judge can offer suggestions for dispute resolution but cannot enforce these opinions.

The two parties agree to open up, or unbind, their books for inspection by the other party.

The client and project organizations both agree to perform exactly what the judge decrees.

The client and project organizations are not bound by the rules of law.

please answer all 5 questions

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!