Question: Question 1 The project was over, so each worker went back to her usual assignment, taking with them the notebook they were issued when the
Question 1
The project was over, so each worker went back to her usual assignment, taking with them the notebook they were issued when the project began. They never were sure whether the project had been successful or unsuccessful, but they could be positive that the project was terminated by:
Group of answer choices
Extinction.
Addition.
Integration.
Starvation.
Question 2
Which two types of project termination are reserved for successful projects?
Group of answer choices
Addition and integration
Integration and starvation
Starvation and extinction
Extinction and addition
Question 3
Of the project closeout management steps listed, the first is to:
Group of answer choices
Finish the work.
Hand over the project.
Gain acceptance for the product.
Review how it all went.
Question 4
A lessons-learned analysis is BEST described as:
Group of answer choices
An organizational learning process.
A bookkeeping process.
A personnel reassignment process.
A pressure relief process.
Question 5
In non-binding arbitration:
Group of answer choices
The judge can offer suggestions for dispute resolution but cannot enforce these opinions.
The two parties agree to open up, or unbind, their books for inspection by the other party.
The client and project organizations both agree to perform exactly what the judge decrees.
The client and project organizations are not bound by the rules of law.