Question: Question # 1 - TOTAL COST ANALYSIS - ABC Plastics bid for a 3 year contract Which of Insourcing or Outsourcing is cheaper and by

Question # 1 - TOTAL COST ANALYSIS - ABC Plastics bid for a 3 year contract
Which of Insourcing or Outsourcing is cheaper and by how much?
INSOURCING:
Machinery: $ 10,000 over the life of the contract Materials : $ .05 per unit
Labour: $.045 per unit Supervision: $ .0165 per unit
Design: $ 30,000 Overhead: $ .03 per unit
OUTSOURCING: bid for 200,000 parts in yr. 1; 300,000 parts in yr. 2; 500,000 parts in yr. 3
Purchase price: $ .10 per unit Shipping + Handling: $ .01 per unit
Inventory Charges: $ .005 per unit Adminstration: $ 20 per month
INSOURCING Item INSOURCE # 1 Cost OUTSOURCING Item OUTSOURCE # 1 Cost
Direct Costs Direct Material $0.0500 Purchase price $0.1000
Direct labor $0.0450 Freight costs $0.0100
Freight costs Inventory $0.0050
Indirect costs Supervision/Admin. $0.0165 Purchasing/Admin. $0.0007 $20 x 36 months
$30,000 Supplies/design $0.0300 Receiving
Maintenance Quality control
$10,000 Depreciation $0.0100
Fixed overhead $0.0300
Total Cost per unit: $0.1815 $0.1157
Savings per unit: $0.06578 Total savings: $65,780

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!