Question: Question 1 What action may be appropriate if you need to compress your project schedule but your management will not provide you with any additional
Question 1
What action may be appropriate if you need to compress your project schedule but your management will not provide you with any additional resources?
Fast Tracking
Crashing
Resource leveling
Resource smoothing
Question 2
What action may be appropriate if you need to compress your project schedule and management is willing to give you additional resources but you can not overlap any activities on the critical path?
Fast Tracking
Crashing
Resource leveling
Resource smoothing
Question 3
What action may be appropriate if you need to compress your project schedule and management is not willing to give you additional resources and you can not overlap any activities on the critical path?
Fast Tracking
Crashing
Reduce scope
Resource leveling
Resource smoothing
Question 4
0.0/2.0 points (graded)
When optimizing the project schedule, the Project Manager must consider:
(select 2)
That Fast Tracking is always a viable option for schedule optimization
What is more important: meeting the schedule or operating within resource constraints
That adding resources to Crash a project can have negative consequences to the project
That Crashing can always be accomplished without increasing costs
Question 5
0.0/2.0 points (graded)
If a decision is made to reduce scope in order to meet a schedule constraint:
(select 2)
The scope reduction could be accomplished by cutting the budget
The scope reduction can be applied to non-critical path activities to reduce risk
Project scope planning documents must be updated to reflect the reduced scope
The scope reduction must be documented and agreed to