Question: QUESTION 1 You are tasked to manage a project with activities and their respective durations as listed in Table 1 below: Table 1 table

QUESTION 1
You are tasked to manage a project with activities and their respective durations as listed in Table 1 below:
Table 1
\table[[Activity,\table[[Immediate],[Predecessor]],\table[[Duration],[(months)]]],[1,NONE,2],[2,1,4],[3,1,2],[4,2,2],[5,2,3,4],[6,1,5,6],[7,4,2],[8,4,5,6,6],[9,7,8,6],[10,8,6,4],[11,8,9,10,]]
1.1 Construct a Gantt chart of the project.
(10)
1.2 Construct a precedence diagram.
(25)
1.3 Determine the critical path for your project?
(5)
[40 MARKS]
 QUESTION 1 You are tasked to manage a project with activities

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!