Question: Question 1 - You decided to open a production facility. The following figure shows the process flow diagram. You hired 5 employees, and each employee
Question 1 - You decided to open a production facility. The following figure shows the process flow diagram. You hired 5 employees, and each employee perlorms one task. A- How many units can you produce in 10 hours? (2) B - Where do you have work-in-process inventory? (show it on the above flow chart) (2) C - What is the labor productivity? (2) D - How many people do you hire at least to make Task A the new bottleneck? (2) Now you decided to eliminate two tasks (so now you have three employees). And the following is the new process design