Question: Question 1 You have collected the data for an oncoming project. The time is in days and the project direct costs are given below. The

Question 1 You have collected the data for an oncoming project. The time is in days and the project direct costs" are given below. The indirect costs for the project are determined on a daily duration basis. The first 12 days will have an indirect cost of $40/day, and every day over 12 days a cost of $60/days. Activity Immediate Predecessor Normal Time Crash Time Normal Cost(Direct) Crash Cost(Direct) 3 2 300 400 None A 3 none 3 100 N W w B A 200 350 1 A 600 3 2 400 D B, C 500 900 1 2 E D N W N w 200 none 3 3 F E 2 100 none G F (Note: (1) You can write only the expression with the actual numbers; (2) If you have to make an assumption, explain it.) A. How long will the project last? B. What is the total cost of the project? C. How much would it cost to finish the project in 14 days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
