Question: QUESTION 10 1. For a process that has total lead-time of 6 hours and value added time of 10 minutes, what is the Process Cycle

QUESTION 10 1. For a process that has total

QUESTION 10 1. For a process that has total lead-time of 6 hours and value added time of 10 minutes, what is the Process Cycle Efficiency? Give answer in percentage QUESTION 11 A plant works ten hours per day, taking a total break time of one hour. If the demand is 54000 units per year and you work 300 days per year, what is your TAKT time (in minutes)