Question: Question 10 (1 point) Problem data: Job A B D E Time (days) since arrival 5 4 3 2 1 Estimated days required 8 7

Question 10 (1 point) Problem data: Job A B D E
Question 10 (1 point) Problem data: Job A B D E Time (days) since arrival 5 4 3 2 1 Estimated days required 8 7 5 12 6 Days until due 11 9 19 22 21 What would be the average tardiness if the EDD rule was used? 1) 4.8 2) 8.0 3) 6.8 O 4) 5.2 Question 11 (1 point) Saved What is the key to achieving small lot sizes