Question: Question 10 (1 point) Saved A project is not going well. Actual costs are significantly over the Plan. A project gate review will occur in

Question 10 (1 point) Saved A project is not
Question 10 (1 point) Saved A project is not going well. Actual costs are significantly over the Plan. A project gate review will occur in the next several days. Which of the following actions would LEAST likely be considered during the review? Conduct a full review of areas of high cost over-runs Postpone the review until the project manager can improve cost performance Terminate the project Make use of the project's Management Reserve