Question: Question 10 12 points Save Answer a. Use the task table to draw a graph with appropriately labeled vertices and edges. b. Find the Minimum

 Question 10 12 points Save Answer a. Use the task table
to draw a graph with appropriately labeled vertices and edges. b. Find

Question 10 12 points Save Answer a. Use the task table to draw a graph with appropriately labeled vertices and edges. b. Find the Minimum Project Time (MPT) of the project. c. Find the Critical Pass (CP). Task Time Prerequisites Start 0 A 1 None B 2 None C 3 A, B D 5 B E 5 C 5 C, D G 4 D, E H 4 E, F Finish Attach File Browse Local Files Browse Content Collection Browse Dropbox