Question: Question 10. In the below network diagram, weighted average times and standard deviations are given; what is the standard deviation of activity D if: Pr

Question 10. In the below network diagram,

Question 10. In the below network diagram, weighted average times and standard deviations are given; what is the standard deviation of activity D if: Pr (complete the project within 67 days) =67% B D t(e)=13 S=3 t(e)=16 S=? A F te=30 S=5 t(e)=5 S=1 E t(e)=20 S=2 t(e)=6 S=2