Question: Question 11 (0.2 points) Referring to the previous problem, how many kanbans would be required if Lead Time for components increased to 30 minutes? (ROUND

Question 11 (0.2 points) Referring to the previous problem, how many kanbans would be required if Lead Time for components increased to 30 minutes? (ROUND to the APPROPRIATE WHOLE NUMBER) Your Answer: Question 10 (0.2 points) An assembly station is asked to process 100 circuit boards per hour. It takes 20 minutes to receive the necessary components from the previous workstation. Completed circuit boards are placed in a rack that will hold 10 boards. The rack must be full before it is sent to the next workstation. If the factory uses a safety stock of 10%, how many kanbans are needed for the circuit board assembly process? (ROUND to the APPROPRIATE WHOLE NUMBER) Your Answer: Answer Question 11(0.2 points) Referring to the previous problem, how many kanbans would be required if Lead Time for components increased to 30 minutes? (ROUND to the APPROPRIATE WHOLE NUMBER) Your
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
