Question: Question 11 (1 point) When the engineering department needs to assemble a printing machine, so the project team can use it to print a new
Question 11 (1 point)
When the engineering department needs to assemble a printing machine, so the project team can use it to print a new book, this is called a(n)
Question 11 options:
| A | External dependencies |
| B | Internal dependencies |
| C | Mandatory dependencies |
| D | Discretionary dependencies |
Question 12 (1 point)
Two tasks A & B. Task A duration is 6 days and Task B duration is 4 days. If the total time to complete both tasks is 10 days, Task B is dependent on Task A with
Question 12 options:
| A | A Finish-to-Start dependency |
| B | A Start-to-Start dependency |
| C | A Finish-to-Finish dependency |
| D | None of the above |
Question 13 (1 point)
Two tasks A & B. Task A duration is 6 days and Task B duration is 4 days. If Task B is dependent on Task A with a Finish-to-Finish dependency, task A must start
Question 13 options:
| A | 2 days after Task B Finishes |
| B | 3 days before Task B starts |
| C | At the same time as Task B |
| D | 2 days before Task B starts |
Question 14 (1 point)
A project team is tasked with estimating a project cost to build a computer network that connect offices on 4 different continents. The team never done this kind of project before. The best approach to estimate the project cost is to use the following cost estimation method
Question 14 options:
| A | Parametric Estimate |
| B | Analogous Estimate |
| C | Bottom-up Estimate |
| D | Top-down Estimate |
Question 15 (1 point)
Two tasks A & B. Task A duration is 6 days and Task B duration is 4 days. If the total time to complete both tasks is 6 days, Task B is dependent on Task A with
Question 15 options:
| A | A Finish-to-Start dependency |
| B | A Start-to-Finish dependency |
| C | A Finish-to-Finish dependency |
| D | None of the above |