Question: Question 11 (2 points) Your boss is the project manager for a large contract assembly plant. She tells you that the learning rate for Product

Question 11 (2 points) Your boss is the project manager for a large contract assembly plant. She tells you that the learning rate for Product C is 0.7 and that the first unit took 23 hours. How long will it take to make the fourth unit of the product? Answer to two decimal places. Your Answer: Your Answer Question 12 (3 points) Your boss is the project manager for a large contract assembly plant. She tells you that the learning rate for Product D is 0.8 and that the first unit took 25 hours. How long will it take to make the twentieth unit of the product? Answer to two decimal places. Your