Question: Question 11 In a particular project, activity D follows immediately after activities B and C For B: ES-4, EF-10 For C: ES-7, EF-12 What is

Question 11 In a particular project, activity D
Question 11 In a particular project, activity D follows immediately after activities B and C For B: ES-4, EF-10 For C: ES-7, EF-12 What is the earliest start ES for activity D? 4 12 10 7 Question 12 In a particular project, activity C and activity D both immediately follow activi For C: ES-16, LS-17 DAN