Question: Question 12 (1 point) How are projects different than programs? Question 12 options: projects are large and programs are small Programs are 2 or more

Question 12 (1 point)

How are projects different than programs?

Question 12 options:

projects are large and programs are small

Programs are 2 or more projects that contribute to the program objective

Programs can be watched closely by management

Projects are more risky than programs

Question 13 (1 point)

read carefully - ProJect scope are the Deliverables of the project and ProDuct scope are the activities needed to build/complete the deliverables

Question 13 options:

True
False

Question 14 (1 point)

A Project Charter has high level information such as high level requirements, high level risks, etc whereas a Scope Statement has detailed information

Question 14 options:

True
False

Question 15 (1 point)

A stakeholder register formally registers project team members so they can be paid

Question 15 options:

True
False

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!