Question: Question 12 (1 point) How are projects different than programs? Question 12 options: projects are large and programs are small Programs are 2 or more
Question 12 (1 point)
How are projects different than programs?
Question 12 options:
|
|
projects are large and programs are small
|
|
|
Programs are 2 or more projects that contribute to the program objective
|
|
|
Programs can be watched closely by management
|
|
|
Projects are more risky than programs
|
Question 13 (1 point)
read carefully - ProJect scope are the Deliverables of the project and ProDuct scope are the activities needed to build/complete the deliverables
Question 13 options:
| True | |
| False |
Question 14 (1 point)
A Project Charter has high level information such as high level requirements, high level risks, etc whereas a Scope Statement has detailed information
Question 14 options:
| True | |
| False |
Question 15 (1 point)
A stakeholder register formally registers project team members so they can be paid
Question 15 options:
| True | |
| False |