Question: Question 12 1.5 points Processing Time (days) 2 8 Job B D E F Due date (days) 7 16 4 17 15 18 4 10

Question 12 1.5 points Processing Time (days) 2 8

Question 12 1.5 points Processing Time (days) 2 8 Job B D E F Due date (days) 7 16 4 17 15 18 4 10 5 12 Given the above processing times (set up times are included) and due dates for a series of jobs waiting to be processed at a work center, what is the SPT sequence of jobs? A-B-C-D-E-F C-A-E-B-D-F OC-F-A-E-B-D O A C-E-B-D-F